The Kosovo government has approved a package of emergency measures for the electricity supply, to be implemented over 60 days. The plan includes using the generating capacity of the Ujman Hydropower Plant, reducing energy consumption by public institutions and taking other steps aimed at ensuring a stable supply for residents and the economy. The decision also requires the approval of the Assembly of Kosovo before it can be implemented.
At today’s government meeting, Prime Minister Albin Kurti said the difficulties in the energy sector were linked to limited domestic generating capacity and Serbia’s blocking of electricity transmission lines.
Të lidhura
None found
According to Kurti, the Ministry of Economy proposed a two-month period of emergency measures lasting 60 days. He said the measures include using the Ujman Hydropower Plant’s capacity to supply universal service customers, reducing consumption by public institutions and taking other steps as the situation may require. The prime minister said the aim was to use existing capacity as efficiently as possible and reduce risks to the supply of electricity for residents and the economy.
Economy Minister Artane Rizvanolli explained that the Ujman Hydropower Plant would be required to generate electricity during periods of peak demand and sell it to the universal service supplier. She also announced the creation of an emergency technical committee to monitor developments and propose further measures to the government if necessary.
Rizvanolli said the decision had been drawn up in light of production constraints and Serbia’s continued blocking of the lines. The measures include requiring the Ujman Hydropower Plant to generate electricity during peak hours and sell it to the universal service supplier for residents and micro and medium-sized enterprises. The decision also requires all public institutions to implement energy-saving measures during this period.
The minister said the emergency technical committee would monitor the situation and submit proposals for additional measures the government could take.
During her report, Rizvanolli also addressed delays in bringing unit B1 of the Kosova B thermal power plant back into operation. She said the European Union’s representative in Kosovo, who serves as the contracting authority for the project to reinstall electrostatic precipitators and reduce nitrogen oxides, had announced that the work would be delayed.
Unit B1 had been scheduled to return to operation on November 25, in accordance with the contract between the EU and the contractor.
In addition to the emergency package, the government has decided to temporarily assign the Kosovo Energy Corporation a public service obligation to secure cross-border electricity transmission capacity.
Rizvanolli explained that the measure is preventive and aims to avoid increases in the cost of cross-border capacity, particularly when transmission lines are congested.
According to the minister, the Kosovo Energy Corporation will be required to secure rights to use a certain amount of cross-border transmission capacity from December 1 to 31, 2026.
She said that in previous years, when other lines were congested, demand rose significantly and prices for cross-border capacity used in electricity trading reached exceptionally high levels. For this reason, the government is proposing the temporary obligation for the Kosovo Energy Corporation to secure rights to use cross-border capacity, specifically for the period from December 1 to 31, 2026.